ROAD MAP TO THE COMMENCEMENT OF CONSTRUCTION OF THE MARKETS.

S/N Activity Time Frame
01 Official Launch of MATIP-1 in Mbale Municipality 19-20 May, 2010
02 Sensitization Meetings of Market Vendors, Opinion and Local Leader May – Dec 2010
03 Preparation and dissemination of Mobilization messages on Radio, Newspapers and Television May, 2010- December 2010
04 Preparation and adoption of temporary vendor Re-location plans June-July 2010
05 Display, review and adoption of designs by leaders of Vas, and  Town Councils August-September 2010
06 Registration and validation of current vendors and display of vendors registers in the markets. August-September 2010
07 Temporary Re-location of Vendors to agree upon sites. August –Oct 2010
08 Procurement of contractors to carry out construction of the markets August-Oct 2010
09 Award  of Contracts and commencement of the Execution of  construction works August- October 2010
10  Ground Breaking Ceremonies Nov.- Dec 2010
 